Belwind Haliade

DECO’s provided dive teams for pile cover removal, pile dredging operations and ROV support throughout the entire project.

Project scope
• Belwind II wind farm | North Sea
• Haliade demo wind turbine | 6MW Pure Torque WTG
• Dive support during pile cover removal
• ROV support during jacket installation
• Diver-operated pile dredging
• Post-installation dive inspections

 

Pile specifications
• 72’’ pile diameter
• 1.5 ton pile covers
• 12 meter dredging depth
• 34m water depth
▸▸ Diver’s operating depth

 

Equipment features
• Dive support vessel M/V Anaïs
▸▸ Dive support activities
• ROV spread
▸▸ In-pile inspection from M/V Osprey
▸▸ Mojave-type ROV
▸▸ Cougar XT Compact - ROV spread
• Hydraulic 12’’ airlift
▸▸ Diver-operated pile dredging