Decommissioning
Leman BH platform | Southern North Sea
Boskalis contracted DECO to cut jacket piles and 8 aligned pin holes for lifting.
DECO was also responsible for the installation of a rigging platform on top of the jacket. The rigging platform allowed access to the inner parts of the jacket piles in a safe way and was equipped with a pedestal crane, used for handling the DECO tools.
Pile cutting and dredging specifications
- Pile diameter: 1219 mm
- Wall thickness of piles: 38,1 mm
- Water depth: 38 m
- Cutting 3 m below seabed